TWINTEC Industrial Floors

The facility is an old factory building. The base consists of old asphalt and old concrete. In some areas, a bedding layer of fine gravel and crushed stone fines was applied.

After base preparation, we get ready for concrete placement. A membrane is laid over the base to prevent moisture loss from the concrete.

The first mixer truck arrives.

When a mixer truck can drive directly into the facility, concrete placement becomes easier, faster, and more cost-effective, as a concrete pump is not required.

Concrete placement from the mixer proceeds quickly.

The next morning, this section looks like this.

The floor surface is perfectly smooth, glossy, and has a uniform color. Good work! Over the next few days, the floor will begin to change color and “bleach.” Light spots and streaks will appear. After a month, the floor will fully dry, the spots will disappear, and the floor will assume its final color.

Pouring the next section of the floor

Joint between fresh concrete and the previous day’s pour

Troweling equipment is positioned next to the fresh concrete for ease of operation during troweling

On solid bases, it is not always necessary to reinforce the concrete. Often, steel, polypropylene, or basalt fiber is sufficient.

Another section of the floor is ready

The hardened top layer (topping) resists abrasion, protects against mechanical damage, and creates a dust-free surface.

The next room is being prepared for pouring

One pouring cycle takes 1 to 2 days of continuous work. The duration depends on the concrete setting time, which in turn is determined by temperature, humidity, and the concrete mix composition. No two pours are exactly alike; we must adapt to specific conditions each time.

The concrete has been placed and is almost troweled

Final troweling is performed using blades. The blades change their angle of attack to create the necessary pressure on the concrete surface.

Immediately after troweling, the concrete surface is sealed with an acrylic varnish. The varnish fills the concrete pores, forms a moisture-impermeable film, and retains moisture in the concrete for proper curing.

The varnish serves only to retain moisture and works during the concrete curing process. It plays no decorative or aesthetic role. After a couple of months of operation, the varnish wears off.

Nighttime pours are common

Good lighting is essential at the site at night. We bring our own floodlights.

The floor is laid. Joints have been cut. The concrete has begun to bleach. It will fully lighten in a month. Racking can be installed in a couple of weeks.

Durostone topping was used on this project—a proven, reliable, and high-quality material produced in Europe.