Construction of an industrial concrete floor at the Nestle plant, Smolyhove village, Volyn region.

The subbase is prepared before concrete pouring.

The planned and compacted subbase is ready for industrial flooring installation.

A double spatial reinforcement mesh is tied according to the project design.

Concrete pouring is performed using laser levels, with constant level monitoring.

Control joints in the slabs are designed to induce cracking in concrete at predetermined locations.

Over several weeks, the floor cures and develops its natural color.

Industrial floors with a hardened topping can operate for decades.